Back to Success Stories
HVAC Equipment|04/2024

HVAC Systems: German Industrial Chillers and AHUs to Latvia

Germany - Latvia|3 days|2 FTL trucks

A new commercial building in Riga needed its climate control system installed before the opening date. 2 truckloads of HVAC equipment from a German manufacturer: a 6-tonne chiller unit and 2 air handling units (AHUs) weighing 3 tonnes each. Crane unloading required - units go directly to the rooftop.

What happened

HVAC units are heavy, oversized, and must be lifted by crane to the building rooftop. The building was in Riga city center - limited crane access, street closure needed. The chiller and AHUs had to arrive on the same morning to match the crane booking.

What made it difficult

  • 16-tonne chiller + 2 x 3-tonne AHUs - crane lift to rooftop
  • 2Riga city center - street closure permit for crane operation
  • 3Both trucks must arrive same morning (5 AM) for crane slot
  • 4Units cannot be tilted more than 15 degrees during lift
  • 5Refrigerant-charged chiller requires careful handling (no impacts)

How we handled it

Street closure permit obtained from Riga City Council 2 weeks in advance. 80-tonne mobile crane booked for 5 AM start. Both trucks arrived at 4:30 AM from our overnight staging point outside Riga. Chiller lifted first (heaviest, most delicate), positioned on pre-built rooftop brackets. Then both AHUs. All 3 units on the roof by 9 AM. Street reopened by 10 AM. The building's HVAC contractor started connections immediately.

Result

Units delivered1 chiller (6t) + 2 AHUs (3t each)
Crane operation5 AM - 9 AM, city center
Street closureReopened by 10 AM
Transit3 days from German factory

HVAC to the rooftop? We coordinate the crane, the permit, and the delivery. +371 22302054 / info@langino.lv